Line 53: | Line 53: | ||
** Trigger and Data Acquisition (TDAQ) ([http://mu2e-docdb.fnal.gov:8080/cgi-bin/ShowDocument?docid=22774 mu2e-docdb-22774]) | ** Trigger and Data Acquisition (TDAQ) ([http://mu2e-docdb.fnal.gov:8080/cgi-bin/ShowDocument?docid=22774 mu2e-docdb-22774]) | ||
** Extinction Monitor (ExtMon) ([http://mu2e-docdb.fnal.gov:8080/cgi-bin/ShowDocument?docid=22831 mu2e-docdb-22831]) | ** Extinction Monitor (ExtMon) ([http://mu2e-docdb.fnal.gov:8080/cgi-bin/ShowDocument?docid=22831 mu2e-docdb-22831]) | ||
** Data Processing and Computing (DPC) ([http://mu2e-docdb.fnal.gov:8080/cgi-bin/ShowDocument?docid=22960 mu2e-docdb-22960] | ** Data Processing and Computing (DPC) ([http://mu2e-docdb.fnal.gov:8080/cgi-bin/ShowDocument?docid=22960 mu2e-docdb-22960]) | ||
* WBS dictionary ([http://mu2e-docdb.fnal.gov:8080/cgi-bin/ShowDocument?docid=25461 mu2e-docdb-25461] | * WBS dictionary ([http://mu2e-docdb.fnal.gov:8080/cgi-bin/ShowDocument?docid=25461 mu2e-docdb-25461]) | ||
** Boundaries between Operations WBS ([http://mu2e-docdb.fnal.gov:8080/cgi-bin/ShowDocument?docid=28701 mu2e-docdb-28701] | ** Boundaries between Operations WBS ([http://mu2e-docdb.fnal.gov:8080/cgi-bin/ShowDocument?docid=28701 mu2e-docdb-28701]) | ||
* ESH&Q Plan for Commissioning and Operations ([http://mu2e-docdb.fnal.gov:8080/cgi-bin/ShowDocument?docid=22972 mu2e-docdb-22972] | * ESH&Q Plan for Commissioning and Operations ([http://mu2e-docdb.fnal.gov:8080/cgi-bin/ShowDocument?docid=22972 mu2e-docdb-22972]) | ||
* Extracted PDF of schedule milestones | * Extracted PDF of schedule milestones | ||
* Extracted PDF of critical path for detector | * Extracted PDF of critical path for detector | ||
* Cost and resource tables per WBS and total roll-up ([http://mu2e-docdb.fnal.gov:8080/cgi-bin/ShowDocument?docid=32497 mu2e-docdb-32497] | * Cost and resource tables per WBS and total roll-up ([http://mu2e-docdb.fnal.gov:8080/cgi-bin/ShowDocument?docid=32497 mu2e-docdb-32497]) | ||
===Mu2e Accelerator Operations=== | ===Mu2e Accelerator Operations=== |
Revision as of 21:19, 7 April 2020
Introduction
Note: some links below are NOT viewable by reviewers yet, but will be viewable by 21 April.
- 05-06 May 2020: Preliminary Operations Planning Review at Fermilab
- Review agenda: mu2e-docdb-32040
- Committee member contact information and writing assignments: mu2e-docdb-32040
- Review charge questions: mu2e-docdb-28221
- Video streaming and phone connection (zoom)
- Mu2e Operations Planning Team contact list
Links to presentations
- Introduction session
- Welcome
- Mu2e science, apparatus, and organization
- Mu2e and ES&H
- Mu2e Detector and Computing Operations session
- Detector and Computing Operations Overview
- Facilities and Solenoids (mu2e-docdb-32476)
- Tracker (mu2e-docdb-32488)
- Calorimeter (mu2e-docdb-32491)
- Cosmic Ray Veto (mu2e-docdb-32367)
- Stopping Target Monitor / Extinction Monitor
- TDAQ / Data Processing & Computing (mu2e-docdb-32344)
- Mu2e Accelerator Operations session
- Overview of Accelerator Operations for Mu2e
- 8 GeV Beam
- Shielding and Loss Control
- Target Station
- Resonant Extraction
Documentation
- Collaboration/FNAL org chart
- Operations risk register (mu2e-docdb-26550 - available 21 April)
- Plan to achieve detailed plan (including metrics)
- Mu2e data management plan (mu2e-docdb-5993)
- Link milestones in Mu2e Operations P6 (mu2e-docdb-27334)
Mu2e Detector and Computing Operations
- Mu2e Preliminary Experiment Operations Plan (mu2e-docdb-31439)
- Requirements documents
- Accelerator milestones (mu2e-docdb-22816)
- Experiment Facilities (mu2e-docdb-22762)
- Solenoids (mu2e-docdb-22498)
- Stopping Target Monitor (STM) (mu2e-docdb-27463)
- Tracker (mu2e-docdb-22804)
- Calorimeter (mu2e-docdb-22786)
- Cosmic Ray Veto system (CRV) (mu2e-docdb-22699)
- Trigger and Data Acquisition (TDAQ) (mu2e-docdb-22774)
- Extinction Monitor (ExtMon) (mu2e-docdb-22831)
- Data Processing and Computing (DPC) (mu2e-docdb-22960)
- WBS dictionary (mu2e-docdb-25461)
- Boundaries between Operations WBS (mu2e-docdb-28701)
- ESH&Q Plan for Commissioning and Operations (mu2e-docdb-22972)
- Extracted PDF of schedule milestones
- Extracted PDF of critical path for detector
- Cost and resource tables per WBS and total roll-up (mu2e-docdb-32497)
Mu2e Accelerator Operations
- Extracted PDF of critical path for accelerator
- link to accelerator documents in mu2e-docdb (viewable by reviewer)
Select Project documentation
- Mu2e Technical Design Report (TDR) (mu2e-docdb-4299)
- Mu2e building transition to operations plan (mu2e-docdb-5844)
- Transition to operations for Mu2e Conventional Facilities occurred Spring 2017
- Rules to estimate uncertainty for Labor and M&S (mu2e-docdb-459)
- DOE Independent Project Review website 10-12 Dec 2019 at link