Mu2ePreliminaryOperationsReview: Difference between revisions
Jump to navigation
Jump to search
Line 4: | Line 4: | ||
Login access to content at links will be emailed to reviewers | Login access to content at links will be emailed to reviewers | ||
<big>The planning for Mu2e Operations has followed the guidelines outlined in the DOE memo describing the Operations planning and review process ([http://mu2e-docdb.fnal.gov:8080/cgi-bin/ShowDocument?docid=21579 mu2e-docdb-21579])</big> | |||
* <b>05-06 May 2020</b>: Preliminary Operations Planning Review at Fermilab | * <b>05-06 May 2020</b>: Preliminary Operations Planning Review at Fermilab | ||
Line 11: | Line 13: | ||
** Video streaming and phone connection (zoom) | ** Video streaming and phone connection (zoom) | ||
** Mu2e Operations Planning Team contact list | ** Mu2e Operations Planning Team contact list | ||
==Links to presentations== | ==Links to presentations== |
Revision as of 14:26, 15 April 2020
Introduction
Content at all links subject to change until 21 April, when they will be frozen for the review.
Login access to content at links will be emailed to reviewers
The planning for Mu2e Operations has followed the guidelines outlined in the DOE memo describing the Operations planning and review process (mu2e-docdb-21579)
- 05-06 May 2020: Preliminary Operations Planning Review at Fermilab
- Review agenda: mu2e-docdb-32040
- Committee member contact information and writing assignments: mu2e-docdb-32040
- Review charge questions: mu2e-docdb-28221
- Video streaming and phone connection (zoom)
- Mu2e Operations Planning Team contact list
Links to presentations
- Introduction session
- Welcome
- Mu2e science, apparatus, and organization
- Mu2e and ES&H
- Mu2e Detector and Computing Operations session
- Detector and Computing Operations Overview (mu2e-docdb-32594)
- Facilities and Solenoids (mu2e-docdb-32476)
- Tracker (mu2e-docdb-32488)
- Calorimeter (mu2e-docdb-32491)
- Cosmic Ray Veto (mu2e-docdb-32579)
- Stopping Target Monitor / Extinction Monitor (mu2e-docdb-32606)
- Stopping Target Monitor Details (mu2e-docdb-32570)
- Target Extinction Monitor Details (mu2e-docdb-32506)
- TDAQ / Data Processing & Computing (mu2e-docdb-32612)
- Mu2e Accelerator Operations session
- Overview of Accelerator Operations for Mu2e
- 8 GeV Beam
- Shielding and Loss Control
- Target Station
- Resonant Extraction
Documentation
- Operations risk register (mu2e-docdb-26550)
- Mu2e data management plan (mu2e-docdb-5993)
- Link milestones in Mu2e Operations P6 (mu2e-docdb-27334)
Mu2e Detector and Computing Operations
- Mu2e Preliminary Experiment Operations Plan (mu2e-docdb-31439)
- Requirements documents
- Accelerator milestones (mu2e-docdb-22816)
- Experiment Facilities (mu2e-docdb-22762)
- Solenoids (mu2e-docdb-22498)
- Stopping Target Monitor (STM) (mu2e-docdb-27463)
- Tracker (mu2e-docdb-22804)
- Calorimeter (mu2e-docdb-22786)
- Cosmic Ray Veto system (CRV) (mu2e-docdb-22699)
- Trigger and Data Acquisition (TDAQ) (mu2e-docdb-22774)
- Extinction Monitor (ExtMon) (mu2e-docdb-22831)
- Data Processing and Computing (DPC) (mu2e-docdb-22960)
- WBS dictionary (mu2e-docdb-25461)
- Boundaries between Operations WBS (mu2e-docdb-28701)
- Mu2e Commissioning and Operations ES&H plan (mu2e-docdb-22972)
- Extracted PDF of schedule milestones
- Extracted PDF of critical path for detector
- Cost and resource tables per WBS and total roll-up (mu2e-docdb-32497)
Mu2e Accelerator Operations
- Extracted PDF of critical path for accelerator
- link to accelerator documents in mu2e-docdb (viewable by reviewer)
Select Project documentation
- Mu2e Technical Design Report (TDR) (mu2e-docdb-4299)
- Mu2e building transition to operations plan (mu2e-docdb-5844)
- Transition to operations for Mu2e Conventional Facilities occurred Spring 2017
- Rules to estimate uncertainty for Labor and M&S (mu2e-docdb-459)
- DOE Independent Project Review website 10-12 Dec 2019 at link