<big>All times Central time</big> | <big>All times Central time</big> | ||
{| | Tuesday 05 May 2020 | ||
{| | |||
|+ Session 1: Introduction (09:00-10:55) | |||
! Time | ! Time | ||
! Talk | ! style="text-align:left;" | Talk title | ||
! Speaker | ! style="text-align:left;" | Speaker | ||
|- | |||
| 10:00-10:10a || Welcome || Deputy Director for Research or CRO | |||
|- | |||
| 10:10-10:40a || Mu2e science, apparatus, and organization || Jim Miller | |||
|- | |||
| 10:40-10:55a || Mu2e and ES&H || George Ginther | |||
|} | |} | ||
* Mu2e Detector and Computing Operations session | * Mu2e Detector and Computing Operations session | ||
** Detector and Computing Operations Overview ([http://mu2e-docdb.fnal.gov:8080/cgi-bin/ShowDocument?docid=32594 mu2e-docdb-32594]) | ** Detector and Computing Operations Overview ([http://mu2e-docdb.fnal.gov:8080/cgi-bin/ShowDocument?docid=32594 mu2e-docdb-32594]) |
Revision as of 15:25, 20 April 2020
IMPORTANT: The Mu2e Preliminary Operations Plan follows the guidelines outlined for the Preliminary Operations Plan in the memo from J. Siegrist to HEP that describes the Operations planning process (mu2e-docdb-21579)
Login access to content at links will be emailed to reviewers. Content at all links subject to change up until the review.
Introduction
- 05-06 May 2020: Preliminary Operations Planning Review (zoom review)
- Review charge questions: mu2e-docdb-28221
- Review agenda: mu2e-docdb-32040
- Committee member contact information and writing assignments: mu2e-docdb-32040
- Video streaming and phone connection (zoom)
- Mu2e Operations Planning Team contact list
Links to presentations
All times Central time
Tuesday 05 May 2020
Time | Talk title | Speaker |
---|---|---|
10:00-10:10a | Welcome | Deputy Director for Research or CRO |
10:10-10:40a | Mu2e science, apparatus, and organization | Jim Miller |
10:40-10:55a | Mu2e and ES&H | George Ginther |
- Mu2e Detector and Computing Operations session
- Detector and Computing Operations Overview (mu2e-docdb-32594)
- Facilities and Solenoids (mu2e-docdb-32476)
- Tracker (mu2e-docdb-32488)
- Calorimeter (mu2e-docdb-32491)
- Cosmic Ray Veto (mu2e-docdb-32579)
- Stopping Target Monitor / Extinction Monitor (mu2e-docdb-32606)
- Stopping Target Monitor Details (mu2e-docdb-32570)
- Target Extinction Monitor Details (mu2e-docdb-32506)
- TDAQ / Data Processing & Computing (mu2e-docdb-32612)
- Mu2e Accelerator Operations session
- Overview of Accelerator Operations for Mu2e
- 8 GeV Beam
- Shielding and Loss Control
- Target Station
- Resonant Extraction
- Response to questions
Documentation
- Operations risk register (mu2e-docdb-26550)
- Mu2e data management plan (mu2e-docdb-5993)
- Link milestones in Mu2e Operations P6 (mu2e-docdb-27334)
Mu2e Detector and Computing Operations
- Mu2e Preliminary Experiment Operations Plan (mu2e-docdb-31439)
- Requirements documents
- Accelerator milestones (mu2e-docdb-22816)
- Experiment Facilities (mu2e-docdb-22762)
- Solenoids (mu2e-docdb-22498)
- Stopping Target Monitor (STM) (mu2e-docdb-27463)
- Tracker (mu2e-docdb-22804)
- Calorimeter (mu2e-docdb-22786)
- Cosmic Ray Veto system (CRV) (mu2e-docdb-22699)
- Trigger and Data Acquisition (TDAQ) (mu2e-docdb-22774)
- Extinction Monitor (ExtMon) (mu2e-docdb-22831)
- Data Processing and Computing (DPC) (mu2e-docdb-22960)
- WBS dictionary (mu2e-docdb-25461)
- Boundaries between Operations WBS (mu2e-docdb-28701)
- Mu2e Commissioning and Operations ES&H plan (mu2e-docdb-22972)
- Extracted PDF of schedule milestones
- Extracted PDF of critical path for detector
- Cost and resource tables per WBS and total roll-up (mu2e-docdb-32497)
Mu2e Accelerator Operations
- Extracted PDF of critical path for accelerator
- link to accelerator documents in mu2e-docdb (viewable by reviewer)
Select Project documentation
- Mu2e Technical Design Report (TDR) (mu2e-docdb-4299)
- Mu2e Project Execution Plan (PEP) (mu2e-docdb-1172)
- Mu2e building transition to operations plan (mu2e-docdb-5844)
- Transition to operations for Mu2e Conventional Facilities occurred Spring 2017
- Rules to estimate uncertainty for Labor and M&S (mu2e-docdb-459)
- DOE Independent Project Review website 10-12 Dec 2019 at link