==Documentation==
==Documentation==


* Operations risk register ([http://mu2e-docdb.fnal.gov:8080/cgi-bin/ShowDocument?docid=26550 mu2e-docdb-26550])
 
* Mu2e data management plan ([http://mu2e-docdb.fnal.gov/cgi-bin/ShowDocument?docid=5993 mu2e-docdb-5993])
* Link milestones in Mu2e Operations P6 ([http://mu2e-docdb.fnal.gov:8080/cgi-bin/ShowDocument?docid=27334 mu2e-docdb-27334])


===Mu2e Detector and Computing Operations===
===Mu2e Detector and Computing Operations===
Line 122: Line 120:
** Stopping Target Monitor Details ([http://mu2e-docdb.fnal.gov:8080/cgi-bin/ShowDocument?docid=32570 mu2e-docdb-32570])
** Stopping Target Monitor Details ([http://mu2e-docdb.fnal.gov:8080/cgi-bin/ShowDocument?docid=32570 mu2e-docdb-32570])
** Target Extinction Monitor Details ([http://mu2e-docdb.fnal.gov:8080/cgi-bin/ShowDocument?docid=32506 mu2e-docdb-32506])
** Target Extinction Monitor Details ([http://mu2e-docdb.fnal.gov:8080/cgi-bin/ShowDocument?docid=32506 mu2e-docdb-32506])
* Cost and resource tables per WBS and total roll-up ([http://mu2e-docdb.fnal.gov:8080/cgi-bin/ShowDocument?docid=32497 mu2e-docdb-32497])
* Mu2e Commissioning and Operations ES&H plan ([http://mu2e-docdb.fnal.gov:8080/cgi-bin/ShowDocument?docid=22972 mu2e-docdb-22972])
* Mu2e Commissioning and Operations ES&H plan ([http://mu2e-docdb.fnal.gov:8080/cgi-bin/ShowDocument?docid=22972 mu2e-docdb-22972])
* Operations risk register ([http://mu2e-docdb.fnal.gov:8080/cgi-bin/ShowDocument?docid=26550 mu2e-docdb-26550])
* Mu2e data management plan ([http://mu2e-docdb.fnal.gov/cgi-bin/ShowDocument?docid=5993 mu2e-docdb-5993])
* Link milestones in Mu2e Operations P6 ([http://mu2e-docdb.fnal.gov:8080/cgi-bin/ShowDocument?docid=27334 mu2e-docdb-27334])
* Extracted PDF of schedule milestones
* Extracted PDF of schedule milestones
* Extracted PDF of critical path for detector
* Extracted PDF of critical path for detector
* Cost and resource tables per WBS and total roll-up ([http://mu2e-docdb.fnal.gov:8080/cgi-bin/ShowDocument?docid=32497 mu2e-docdb-32497])


===Mu2e Accelerator Operations===
===Mu2e Accelerator Operations===

Revision as of 16:10, 20 April 2020

IMPORTANT: The Mu2e Preliminary Operations Plan follows the guidelines outlined for the Preliminary Operations Plan in the memo from J. Siegrist to HEP that describes the Operations planning process (mu2e-docdb-21579)

Login access to content at links will be emailed to reviewers. Content at all links subject to change up until the review.

Introduction

  • 05-06 May 2020: Preliminary Operations Planning Review (zoom review)

Links to presentations

All times Central time

Tuesday 05 May 2020

Introduction (09:00-10:55)
Time Talk title Speaker
9:30-10:00a Full committee executive session (closed) John Kogut
10:00-10:10a Welcome Deputy Director for Research or CRO
10:10-10:40a Mu2e science, apparatus, and organization Jim Miller
10:40-10:55a Mu2e and ES&H George Ginther
10:55-11:05p BREAK
Session 1: Mu2e Detector and Computing Operations (11:05a-2:25p)
Time Talk title Speaker
11:05-11:55a Mu2e Detector and Computing Operations Overview Greg Rakness
11:55-12:15p Facilities and Solenoids Russ Rucinski
12:15-12:45p WORKING LUNCH
12:45-1:05p Tracker Monica Tecchio
1:05-1:25p Calorimeter Simona Giovanella
1:25-1:45p Cosmic Ray Veto Craig Group
1:45-2:05p Stopping Target Monitor / Extinction Monitor Kevin Lynch
2:05-2:25p TDAQ / Data Processing & Computing Rob Kutschke
2:25-2:35p BREAK
Session 2: Mu2e Accelerator Operations (2:35p-4:45p)
Time Talk title Speaker
2:35-3:05p Overview of Accelerator Operations for Mu2e Jerry Annala
3:05-3:25p Off-Project Activities Steve Werkema
3:25-3:45p 8 GeV Beam Diktys Stratakis
3:45-4:05p Shielding and Loss Control Dean Still
4:05-4:25p Target Station Dave Pushka
4:25-4:45p Resonant Extraction Vladimir Nagaslaev
4:45-5:45p Full committee executive session (closed) John Kogut


Wednesday 06 May 2020

Q&A and closeout (9:30a-3:00p)
Time Talk title Speaker
9:30-10:30a Response to reviewer questions Greg Rakness
10:30a-2:00p Full committee executive session (closed) John Kogut
2:00-3:00p Closeout Presentation
3:00p ADJOURN

Documentation

Mu2e Detector and Computing Operations

Mu2e Accelerator Operations

  • Extracted PDF of critical path for accelerator
  • link to accelerator documents in mu2e-docdb (viewable by reviewer)

Select Project documentation